Building
America Industrialized Housing Partnership
TRIP
REPORT
Clayton
Homes Plant, Waycross GA
Plant
visit and testing
DATE
July 20,
2001
ATTENDEES
David
Beal, Neil Moyer – FSEC
George
Perkins-General Manager, Wendall
Morgan-Service Manager, Joel Beasley-Production Manager,
Darlene Wright-Quality Control Manager,
and Les Rodgers-Material Manager
TRIP
REPORT DISTRIBUTION LIST
George
James, Keith Bennett – DOE
Subrato
Chandra, Neil Moyer, David
Beal, Dave Chasar, Janet McIlvaine– FSEC
George
Perkins, Tom Rehrig – Clayton
Homes
INTRODUCTION
Clayton
Homes, a new BAIHP partner, is currently
looking at improving their duct systems
and considering providing an EnergyStar
product. Leakage from duct systems
is recognized nationally as a major
cause of energy waste, poor indoor
air quality, and poor durability in
site-built and manufactured housing.
Supply duct leakage and inadequate
return air pathways can cause significant
negative pressures within the building.
Negative pressures pull in outside
air (which if located in the hot, humid
South) that can result in severe moisture
damage to building envelope assemblies.
Recognizing this, BAIHP partner Clayton
Homes in Waycross, GA requested the
Florida Solar Energy Center (FSEC)
personnel to inspect their plant, concentrating
on the duct systems, and recommend
improvements to the systems.
PURPOSE
This
was the first visit to examine
the various factory assembly processes
of the Waycross GA, Clayton Homes’ plant.
The Waycross plant currently
produces about six floors per day
and employs approximately 125 people.
The primary focus was on the duct
system construction processes and
assemblies that might affect building
performance and energy efficiency.
This facility manufactures both
single- and double-wide housing
units with a sheet metal ductwork
within the floor system or an overhead
duct system made with fiberglass
ductboard and flex-duct.
DESCRIPTION & FACTORY
TOUR OBSERVATIONS
Duct system
- The metal in-line duct is made in
a continuous piece, the ends are sealed
by cutting and folding the end of the
duct and holding it closed with foil
tape. (See figures at end of report).
This
process of sealing one end requires
approximately 12 feet of foil tape,
2 feet of sheet metal duct and
5-8 minutes of labor to complete.
The
floor registers are placed directly
on top of the supply duct. After
the floor is decked, holes are
cut in the floor (using a circular
saw) for the riser installation.
The metal trunk line is cut freehand
on three sides with a utility
knife and folded over. The riser
is then placed in the hole, tabbed
over and sealed with a foil tape.
The tape is pressed into place
by hand. When the air handler
is installed at the factory,
typical with a floor system,
a plenum is installed. This is
accomplished by cutting a hole
in the deck and in the duct.
The air handler plenum is installed
into the duct using tabs and
foil tape. It is screwed into
the floor decking to hold it
in place. (This was not observed
at the time of visit, but is
how it was described to us.)
As
currently done, the floor metal
duct assembly needs improvement.
The end cap construction is somewhat
time consuming, and utilizes
a fair amount of metal duct and
foil tape. The alignment of the
metal trunk line is not very accurate,
often resulting in the duct to
be misaligned by as much as a
couple of inches (See figures at
end of report). The duct is aligned
by measuring from the edge of the
floor to the edge of the duct
and then held in place with strapping.
The strapping allows sideways
movement of the duct. This makes
the installation of the plenum
and risers difficult at best. As
the metal isn’t
cleaned before taping, the
tape adhesion will probably fail,
allowing the over sized holes to
become a leak path.
The
attic supply ductwork is composed
of flex duct and fiberglass ductboard.
(See figures at end of report).
Collars are inserted into a hole
made in the boxes created with
a utility knife in a freehand
fashion. There is a hole cutting
tool on hand, but not used for
whatever reason. The collars
are held in place with tabs (tape
and/or mastic are not used).
The supply boots are taped together
and held in place with a foam
sealant. The tape that is used
is manufactured by the Ideal
Tape Company, and is a UL-181A-B
pressure sensitive foil tape.
The tape had a date stamp of
10/00, which means the tape is
9 months old. According to the
manufacturer, this tape has a
useful shelf life of 12 months – when
stored in a cool, dry place
(60-80degF and 50% relative humidity).
The flex duct is attached to
the boot collar using two collar
ties, on both inner liner and
then on the outer liner. The
factory personal use a tensioning
tool to attach the straps.
There
are four areas of worth noting concerning
the attic flex systems:
• The
length of the flex duct between connection
points is not being cut to proper
length. Many of flex ducts observed
were excessive in length. This
lends itself to unnecessary bending
and kinking which restricts airflow.
Also, the extra length of duct
also reduces the airflow through
the system.
• The
extra length of flex duct displaces
the area for the attic insulation – thus
reducing the overall attic insulation
levels.
• The
insulation and outer liner of the
flex duct do not always adequately
cover the flex duct collars.
This may lead to condensation
on the exposed metal collars
in the hot, humid attic during
air conditioning usage.
• One
of the flex duct-to-collar connections
had the inner tie strap misaligned.
This resulted in reducing the duct
diameter by nearly 50%.
Although
assembly of various fiberglass boxes
were not observed, ceiling ducts could
be made more air tight if mastic was
used to assemble the systems. The system
is assembled with no sealing of the
collars where they go into the fiberglass
duct board boxes. Sealing this junction
with mastic will improve the air tightness
of the system and increase the strength
of the duct system. This is most important
on the riser ducts (from crawl space
to attic) supplying the system. These
are large ducts, and subjected to high
pressure, as they are closest to the
air handler fan.
Return
Air Pathways - The current
practice for sizing of the return
air pathways from the bedrooms and
through utility doorways follows
the HUD code procedure (Manufactured
Home Construction and Safety Standards
3280.715(b)(4)). This results in
the undersizing of return air pathways
for two reasons:
• Bathroom
areas with bedrooms or other closed
off areas are not included,
• The
airflow calculations are based on
heating system flows, not cooling
system.
Provisions
need to be made to address these
issues by increasing return air
pathways. This can be done by
increasing current pathways and/or
adding addition pathways. The
utility room acting as a return
plenum is of concern. When the furnace
or air handler unit pulls it’s
air from the utility room, and that
room can be closed off by a door, then
the room acts as a return plenum. This
will cause the room to go into a negative
pressure with reference to outside
(as well as the rest of the house).
Return air will come from the house,
but also from all of the other holes,
cracks and openings that exist in that
room. A better system would not use
the utility room as a return plenum,
or make the room extremely “leaky” to
the rest of house to preclude any
pressure difference between the utility
room and the rest of the house.
The air
handler or furnace blower speed used
for cooling may also be a way to reduce
airflow into various rooms. Typically,
the cooling tap of 3 and 4 speed blowers
is set on the high speed. The heat
gain calculations done on the home
should provide not only the model of
the unit needed, but also the flow
of air needed to each zone. The blower
speed selection should match this calculation.
(Note: as an additional benefit, when
the blower speed is reduced, dehumidification
increases.)
House
Ventilation -All of the units
inspected used positive pressure
system. This is a 5 inch flex duct
connected to the top of the air handler
and pulls air from the exterior every
time that blower operates.
Envelope -
The belly board is attached
as a complete assembly – no
tears or holes. As the floor
migrates through the factory,
intentional and unintentional
holes and tears are introduced.
The standard for patching is
with belly tape and staples.
Pervious experience that the
authors have had with this type
of closure system has shown that
it tends to fail over time. This
exposes the floor cavity to the
crawlspace environment. A more
permanent solution needs to be
found for factory and field applications.
• Marriage
line walls appear to have various
irregularities that would prevent
a tight closure. (See figures
at end of report). Three areas
were noted that would cause this:
• The
bottom plate of the end wall juts
out past the floor system.
• The
roof assembly and top of end wall
are not in line. A spacer has
been placed on the end wall to
partly compensate.
The trimming
of the floor decking was out of line
with the end plate. This was probably
due to staples or other debris that
caused the trimming router to move
out of line.
Insulation
of the floor assembly is
done with unfaced fiberglass
batt material. The walls are
insulated with fiberglass batts
(some in plastic wrap and some
unfaced – see
sidebar). It appears that the
insulation is being applied correctly.
The attic insulation is a mineral
wool loose blown application.
The installation of insulation
around the attic flex duct systems
is generally of concern. It is
possible for large areas of ceiling
to be missed or not completely
insulated because of the ductwork
being in the way.
TESTING
While
at the plant, FSEC personnel performed
some simple building airtightness and
duct testing on a recently built single-wide
home (Model: CU16763A, Serial NO: WHC011643GAA).
(See figures at end of report). This
home had an in-line metal floor duct
system with a furnace.
Blower
door test - A blower door
test was done to determine the airtightness
of the building envelope. As a general
rule of thumb, typical values of
building airtightness range between
0.75 and 1 CFM50 per square foot
of conditioned floor area. This house
has a floor area of 1216 ft2 and
a CFM50 of 860 or 0.7 CFM50 per
square foot – a tighter home.
Duct
system test - A duct system
airtightness test was also completed.
A duct tester was attached to the
air handler unit. The supply registers
were temporarily sealed off and the
system was then depressurized to
25 pascals. The total and outside
leakage flow components were measured.
An airtight duct system would have
zero leakage or both the CFM25total and
CFM25out would be 0. Generally,
acceptable values are 6% of floor
area for CFM25total and
3% for CFM25out.
Measured
Duct System Airtightness |
Acceptable
airtightness |
CFM25total =
159 |
73 |
CFM25out =
30 |
36 |
In
this case, it appears that
the leakage to the outside is very
small and in fact passes
the acceptable criteria. However,
this can be misleading. The reason
for the very low leakage to outside
is due to the tightness of
the belly board. A 3 pascal pressure
difference was measured between
the floor cavity and the house
when the house was depressurized
to 50 pascals with the blower
door assembly. This means that
the floor cavity can be considered
within the house (as designed). Problems
will occurs if and when the
belly board integrity is compromised.
This may result from transport,
setup and/or damage at some
future time. When the belly board
is compromised the duct leakage to
the exterior will likely approach
the total leakage – which
is unacceptable.
Inspection
of the duct system revealed a large
hole in the duct where a riser
had been installed, caused by the
duct tearing when the flap of duct
was folded back (See figures at
end of report). This was also observed
in the floor area during the plant
inspection. A better solution would
be to cut all four sides of the
duct, using a template to guide
the cutting operation, or use the
tabless riser shown to plant personnel.
The tabless riser is screwed down
to the trunk duct, and the hole
is then cut out, using the riser
as a guide.
A
double-wide unit was also going
to be tested. This proved impractical,
as the crossover collars had not
been cutout in the belly board.
An inspection by the factory personal
revealed that the crossover collar
had not been installed or perhaps
was installed in the wrong location.
Conversations with the Service
Manager revealed that this has
been a problem that he has been
dealing with during setup.
The
double-wide unit used the
utility room as a plenum.
This room will experience
negative pressures with reference to the outside
any time the air handler/furnace operates and the door
to the utility room is closed.
(The problem will be exacerbated when the dryer operates.)
Air will pass through the door undercut and grill
as designed, however it will also enter around
the ceiling light fixture, plumbing penetrations and
electrical penetrations as the grill and door undercut
do not provide adequate return
air pathways. The electrical
service panel will be a prime candidate for air
entry. It is possible that condensation may be severe
enough to cause rusting of metal parts and even
water running down the wall.
RECOMMENDATIONS
Duct
systems - Improve construction
and sealing techniques. Avoid
excessive runs of flex duct.
Consider use of a end cap for
metal systems. Consider the use
of mastic where possible. Strive
to reach a duct sealing standard
that is 3% of the floor area
of less in the factory.
Return
air pathways -Consider
increasing the pathways for air
from the closeable rooms to the
return grill (jump ducts, larger
transfer grills, etc.). Placement
of the return grill in the common
space should be prioritized (as
opposed to a utility room return).
Verify
airflow requirements in cooling
mode. Adjust blower if necessary.
Belly
board - Improved sealing
techniques that are long lasting
and durable.
Insulation
- Verify insulation levels
around attic installed duct work.
Marriage
lines - Ensure a flat
surface for the mating of the
sections. Consider a factory
installed marriage line gasket
(closed cell) that is durable
and will fill the gap. A gasket
of at least 1 inch thickness
should be considered. Several
commercial products are available
that will work well.
For
questions concerning this trip
report please contact Neil Moyer
or David Beal at FSEC, 321-638-1000
or e-mail nmoyer@fsec.ucf.edu or david@fsec.ucf.edu.
Clayton
Homes – Waycross,
GA |
Closing
inline duct |
Clamp
tool used to make
end fold |
Duct
end ready for foil
tape |
Duct
taped and within
floor assembly |
Misaligned
duct and riser cutout |
Oversized
cutout resulting
in holes |
Riser
with tape applied |
Attic
flex with many bends
and kinks |
More
excessive flex duct |
Double
bend flex kink |
And
more kinked flex |
Flex
to box connection |
Inner
liner squeezed closed |
Electric
furnace with ventilation
duct |
Collar
cutout is not circular |
Marriage
line not flush at
top |
Marriage
line not flush at
bottom |
Trimming
of floor along marriage
line not straight |
Irregular
trimming of marriage
line caused by nail |
Exterior
insulation |
Tested
house |
Duct
system testing |
Duct
leakage at main to
riser connection |
Blower
door test |
Compliance
form |
The
design |
Utility
room as return plenum |