- G.W. Robinson Builder/Developer
|
Figure 35. G.W. Robinson Builder is committed
to meeting Building America and the Florida Green Building
Coalition standards in all Cobblefield homes. |
This builder, a leading member of the BAIHP program, takes
care to incorporate features and measures that enhance not
only the energy and resource efficiency, but also the indoor
air quality, safety, durability, and comfort.
In the Cobblefield Development, G.W. Robinson committed to
building the first "green homes" community, as designated
by the Florida Green Building Coalition (FGBC), and to achieving
Building America standards in each home built. (Please see
Figure 35.) Individual home performance testing by Florida
HERO will ensure that the homes meet both program specifications.
G.W. Robinson proudly alludes to these programs in weekly
newspaper ads. (Please see Figure 36.)
Initial discussions between Florida HERO and the builder,
sales manager, project manager, and mechanical, insulation,
and solar system subcontractors resulted in the original decision
to include batch solar water heating and hydronic heating
systems. Model return air system redesigns now insure proper
mastic duct seals and air sealing techniques. Field tests
showed that due to high pressures at air handlers, leaks on
the return side of the air handler depressurized the mechanical
rooms. When the ceiling was not properly sealed, air from
the attic was introduced to the home, which diminished indoor
air quality, increased summer latent loads, decreased comfort,
and increased the home's operating costs. While many builders
are reluctant to move the entire distribution system into
the thermal envelope, many local builders now are willing
to make some protocol changes.
A portion of the of the return air system redesign in the
Cobblefield Development included reviewing air tightness deficiencies
in the distribution systems and the associated air handler
closets. In response to an ongoing challenge to achieve a
reasonably air tight mechanical equipment closet, one protocol
change shifted ceiling ductboard installation to rough-in,
which allowed maximum accessibility for the field technicians.
Once the main supply and return trunk line were stubbed out,
the ductboard was custom cut and installed over the ducts,
then affixed to framing members with nails or screws and plastic
grommets. The duct line seam between the ceiling and duct was sealed with pressure sensitive tape and
mastic and perimeter seams were caulked after sheetrock installation.
A flow hood CFM test on a Cobblefield model found less than
a 5% deviation from the anticipated design flows.
|
Figure 36.G.W. Robinson Builder runs this
ad every Saturday and Sunday in the Gainesville Sun
newspaper and in the monthly special section "Home Showcase"
over the past two years. The ad touts the builders
involvement in both Building America and
the Florida Green Building Coalition. |
Initially,
Florida HERO recommended using hydronic heating systems for
the Cobblefield Development. Since the original decision
to include these systems, additional County requirements for
anti-scald mixing valves and automatic air vents have added
to the difficulty and precision of system installations.
Larger models also required bigger water heating units which
proved difficult to locate and costly. Installation irregularities
and inconsistencies, despite repeated training attempts, exacerbated
the situation and compromised the envelope tightness. While
the hydronic system offers many benefits, Florida HERO no
longer thought that the benefits justified the costs and problems
associated with installing these systems in this development.
Instead, a cost effective line of high efficiency (.90 AFUE)
condensing natural gas furnaces will replace the hydronic
systems in all 17 models. This furnace style uses PVC for
the exhaust flue and to deliver outside combustion air. This
eliminates the need for high and low combustion air and insures
the maximum amount of system location flexibility. Changing
the heating system type did not affect the model duct designs.
Reducing
Home Moisture After Plumbing Leaks: Florida HERO surveyed, performed diagnostic tests, and made
recommendations to G.W. Robinson on how to prevent moisture-related
problems in several water damaged homes. Two homes had significant
moisture problems with one home flooded several days before
it was scheduled to show in the 2002 Gainesville Fall Parade
of Homes. The "flood" in this home was likely a
result of a material failure in a kitchen sink supply riser.
The large plumbing leak, however, did provide researchers
with the opportunity to initiate and monitor the "drying
out" process.
Interior, exterior, and internal ambient moisture readings
enabled the monitoring of this situation with a goal of preventing
mold growth. To begin the process, all carpets and cabinets
were removed from the home and discarded. Two commercial
dehumidifiers and several fans were installed to reduce the
home's humidity. After 24 hours, moisture readings were taken
at a variety of points throughout the home. Wall surface
moisture readings ranged from 45% to 99%. After five days
of continuous drying, no surface moisture reading exceeded
10.9% at any point in the home. The process and procedures
employed at this time seem to have been successful.
Eliminating the effects of a plumbing line leak and the resulting
water damage proved more difficult in the second home where
the lasting effect of the water damage was mostly odor. Based
on recommendations from FSEC and Florida HERO, the home's
water heater was disconnected, all water-damaged sheetrock,
wood, and insulation removed and replaced, and the water heater
reconnected. Though initially this fix seemed to work, the
smell eventually reappeared. Because the odor was evenly
distributed through the home, further investigation determined
that the odor source was most likely airborne. The air handler,
distribution system, and carpeting were fogged with "May-Clean"
solution, whose active ingredients include "cleaning
solutions and caustic acids." For now, this appears to have
eliminated the home's odor problem. The home was sold and
now is occupied. So, additional data collection may be difficult.
High
Bill Complaint: G.W. Robinson's sales manager expressed concern that the model
center's monthly utility bills were significantly higher then
they expected - more than $300 a month! To locate the source
of this high electric usage, Florida HERO arranged a site
survey with the mechanical contractor and conducted a two-week
temperature/humidity study. Since the home had been individually
performance tested for both whole house infiltration and duct
leakage rates, the detective work was fairly simple. After
determining that the mechanical equipment was correctly functioning
and properly charged, researchers tested the flow rate of
the outside air intake with an Energy Conservatory exhaust
fan flow meter. Higher than anticipated readings, led researchers
to test the return air plenum temperature. With an indoor
temperature of 77° and an outdoor temperature of 93°, the
air temperature in the plenum measured 84°. The in-line damper
was adjusted to reduce the volume of outside air introduced.
While investigating this problem, researchers also noted that
sales staff continually overrode the programmable thermostat,
typically after returning from lunch. Indoor temperature
readings as low as 71° were recorded in the model. All findings
were reported to the builder and subsequent measurements have
indicated that utility bills have dropped.
Standardized
HVAC Installations: Florida
HERO developed duct designs for all of the community
models. Prior to this, the distribution system was field "designed"
by the duct mechanic. To insure that mechanical design specifications
are correctly interpreted by the HVAC installer, Mr. Robinson
has agreed to allow the mechanical contractor to conduct a
final review of all architectural CAD drawings before each
house project begins. With the designer and installer in
agreement on installation parameters, placing the design emphasis
on performance excellence and standardization of supply and
return register size, HVAC installation has proven to be more
timely and the installer's profits enhanced.
Florida
Green Building Certification:
Researcher met with University of Florida Urban Horticulture
Extension Agent, Wendy Wilber, at the Cobblefield model center
to survey and complete the FGBC checklist required by the
green certification process.
Fluorescent
Lighting: Florida HERO
used an infrared thermometer to demonstrate to the builder
the operating temperature differential between an incandescent
(IC) and compact fluorescent (CF) bulb. After viewing operating
temperature differentials of 75° (IC bulb measured 158°, while
the CF bulb measured 83°), the builder indicated an interest
in replacing as many bulbs as possible with CF bulbs.
|