Publication
Index:
Appendix A: Examination of Single Factory's Progress
A
review of progress at a single factory gives a sense of
the process of improving duct systems. Data and observations
here are from a factory visited in February, April, and
July of 2000. Initially, the duct systems were at Qntotal=10%.
The
factory managers set out to achieve the Qntotal
≤ 6% goal,
in preparation for building homes under the EPA Energy Star
Program for Manufactured Housing. The managers and staff
reached the goal by the third visit.
February 2000
The
initial visit revealed that the factory was already using
mastic. Two randomly selected sections were tested. Floor
1, a floor system, measured a Qntotal=10% falling
short of the tightness goal. Floor 2, an overhead system,
measured a Qntotal=5% meeting the goal.
Several
problems with floor system assembly were observed and brought
to the managers' attention in a trip report. These included
misalignment of the trunk duct with the floor risers/boots
cutouts; free hand hole cutting; insufficient mastic application
to seal the floor boots, crossover collars, and furnace
plenum; and loose straps.
Researchers
recommended:
- Circle
cutting tools
- Strap
tightening tools (for flex duct zip ties)
- Improve
placement of trunk ducts under riser holes precut in the
sub-floor,
- Templates
for cutting holes in the trunk duct to improve dimensional
matching with the risers
- Increasing
the size of the bead of mastic applied to joints.
April 2000
The
second visit was to evaluate progress in implementing the
recommendations made and achieving the goal of duct tightness,
Qntotal ≤
6%.
No
ceiling systems were tested based on the performance found
during the first visit and observation that all recommendations
for overhead systems in the Trip Report had been implemented.
Observation
of the floor system assembly found that alignment had improved,
however, other issues were still unresolved:
-
Holes for cross over collars and floor risers were still
being cut free hand, leading to a host of assembly difficulties.
For example, trunk duct holes were being cut too large,
making riser attachment difficult and sometimes impossible.
- Workers
were confused about where to seal the furnace plenum
- Not
all the duct joints were being sealed
- Some
joints were not getting adequate mastic
These
improvements and remaining challenges were reflected in
test results. Researchers tested two randomly selected sections
with floor systems. Floor 1 measured a Qntotal=7%, down
from 10% but just shy of the 6% goal. Floor 2 proved even
closer to the goal at Qntotal=6.3%.
Recommendations
reemphasizing the need to address these observed issues
were detailed in a Trip Report.
July
2000
The third visit to the factory found substantial improvement
to the floor duct system which was reflected in the test
results. Three randomly selected houses were tested:
House
1
Floor 1 CFM25total=45 (AHU side)
Floor 2 CFM25total=27 (non-AHU side)
Combined CFM25total=72
Combined Qntotal=5.4%
House
2
Floor 1 CFM25total= 43(AHU side)
Floor 2 CFM25total= 30(non-AHU side)
Combined CFM25total=73
Combined Qntotal=4%
House
3
Floor 1 CFM25total= 46(AHU side)
Floor 2 CFM25total= 16(non-AHU side)
Combined CFM25total=62
Combined Qntotal=3.8%
All
three houses met the Qntotal = 6% goal after the
recommendations for assembly improvement were implemented.
This factory’s experience echoes that of other factories
that BAIHP has worked with.
Continue
to Appendix B - Duct Leakage and House Pressure Concepts >> |