Reference Publication:   Chandra, Subrato, Neil Moyer, Danny Parker, David Beal, David Chasar, Eric Martin, Janet McIlvaine, Ross McCluney, Andrew Gordon, Mike Lubliner, Mike McSorley, Ken Fonorow, Mike Mullens, Mark McGinley, Stephanie Hutchinson, David Hoak, Stephen Barkaszi, Carlos Colon, John Sherwin, and Rob Vieira. Building America Industrialized Housing Partnership, Annual Report - Fifth Budget Period. 4/1/03 - 3/31/04.
Building America Industrialized Housing Partnership, Annual Report - Fifth Budget Period

5. BAIHP PROJECT MANAGEMENT

BAIHP project management includes participating in Building America program reviews/meetings and preparing monthly and yearly reports for project activities as well as managing all project tasks (see Sections 1-6) and subcontracts. In the 5 th Budget Period, BAIHP also held a Project Review Meeting at FSEC in January 2004 to give interested parties an opportunity to give feedback to the project management team. A list of project management activities is included in Table 57.

Note that only project management activities for the current budget period are available here; if activities from previous budget periods are desired, please contact BAIHP project manager Subrato Chandra at subrato@fsec.ucf.edu or through the BAIHP web page at www.baihp.org.

Table 57 BAIHP Project Management Activities for the 5 th Budget Period

BAIHP Task/Staff

Description/Subject

Month

Task: Participation in BA Quarterly Review Meetings

Chandra
Fairey, Chandra
Chandra
Chandra, McIlvaine

Washington DC. attendee
Washington DC, presenters
Washington DC, presenters
Washington DC, attendees

APRIL 03 JULY 03
DEC 03
FEB 04

Task: Participation in other BA Meetings

Vieira, McIlvaine

DOE Meeting in Washington DC.
McIlvaine presented "Challenges to Implementing Resource Efficiency," a summary strategies gleaned BAIHP and EEIH projects and experience.

MAY 03

Colon

SWA and BIRA expert review meetings in CA.

JUNE 03

McCluney

BAIHP Project Fenestration Tasks Summary Report for work performed in June 2003

JUNE 03

Chandra

Responded to information requests from DOE headquarters.

Through-out the budget period

Task: Prepare 4th Budget Period Progress Report

Chandra, All Researchers

Compiled and summarized results from 4 th Budget Period
Report completed.

APR 03

DEC 03

Prepare Monthly Reports

Chandra, Alidina, All

Compiled and summarized monthly results from research, implementation research, presentations, and publications.

APR 03-MAR 04

Manage Project and Subcontracts and Perform Related Activities

Chandra

FY03 BAIHP subcontracts issued.

JULY 03

Chandra

Met with WSU staff to coordinate 5 th budget period activities and plan for 6 th budget period.

OCT 03

Chandra

Continued meetings and discussions with Sam Taylor regarding Building America deployment through Energy Extension services

FEB 04

Chandra

Continued proposal preparation for BAIHP FY04 funding.

FEB 04

Chandra

Preparation of FY05 AOP proposal submission to DOE.

MAR 04


Project Review Meeting at FSEC

Chandra

Planned BAIHP Project Review meeting at FSEC.

OCT 03-JAN 04

Chandra, All Researchers

Hosted BAIHP Project Review Meeting (2 days) at FSEC with participation from industry partners and DOE.

JAN 04



Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.

Home | Overview | Activities | Team Members | Case Studies
Current Data | Publications | Researchers | Contact Us


Copyright © 2004 Florida Solar Energy Center. All Rights Reserved.

Please address questions and comments regarding this web page to BAIHPMaster