You are here: BAIHP > Publications > Achieving Airtight Ducts
FSEC Online Publications
Reference Publication: McIlvaine, Janet, David Beal, Neil Moyer, Dave Chasar, Subrato Chandra. Achieving Airtight Ducts in Manufactured Housing. Report No. FSEC-CR-1323-03.
Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.
Achieving Airtight Ducts in
Manufactured Housing
Florida Solar Energy Center (FSEC)

Publication Index:

Duct Tightness Data

Duct tightness data presented have been gleaned from BAIHP Trip Reports with some supplementary data from the preceding program, the Energy Efficient Industrialized Housing Project.

Testing Protocol

All duct systems tested were in newly manufactured homes using industry standard methods as delineated in the Minneapolis Blower Door and Duct Blaster User Guides and augmented by the Florida Home Energy Rating requirements where appropriate.

Factory Visits and Test Results Summary

FSEC-BAIHP data spans 1996-2003 and includes test results from 39 visits to 24 factories of six HUD Code home manufacturers (Table 5). Researchers conducted tests on 101 houses representing 190 floors[3]. The data is a compilation of test results from standard production duct systems, repaired to improved production systems.

For a description of improvements implemented at a single manufactured housing plant, see Appendix A.

Average, maximum, and minimum duct leakage data are presented in Table 6 and Figure 7 with similar data from a study published by the Manufacture Housing Research Alliance for comparison (MHRA, 2003.) Figures 8-11 show all data points for Qntotal and QnOut. for taped systems (Fig. 8 and 9) and mastic sealed systems (Fig. 10 and 11).

For mastic sealed systems (n=132), average Qntotal=5.1% (n=124)  with 85 systems achieving the Qntotal 6% target (Fig. 10). Average QnOut=2.4% (n=86) with 73 systems reaching the Qnout 3% goal (Fig. 11).

For taped systems (n=58), average Qntotal=8.2% (n=56) with 19 systems reaching the Qntotal 6% target (Fig. 8). Average QnOut=5.7% (n=30), more than double the mastic average, with 5 systems reaching the Qnout 3% goal (Fig. 9).

The average QnOut found in this data for mastic sealed systems was 2.4%. This correlates with the Manufactured Housing Research Alliance's study which found an estimated average QnOut of 2.5% in 59 floors tested after duct repairs at 16 factories (MHRA, 2003). MHRA did not report the total leakage (measured) used to estimate leakage to the outside, leakage for taped, or leakage for systems before repair.

Table 6 Summary of Findings  (see also, Figures 7-11)

 

BAIHP

MHRA

Tape

Mastic

Mastic, Repaired

Floors Tested

58

132

59

CFM25total (cfm)

71 avg (n=56)
210 max
13 min

43 avg (n=124)
90 max
16 min

NA

CFM25Out (cfm)

49 avg (n=30)
186 max
13 min

23 avg (n=86)
216 max
0 min

NA

Qntotal

8.2% avg (n=56)
18.9% max
1.7% min

5.1% avg (n=124)
10.2% max
1.6% min

NA

Qntotal ≤ 6%

19

85

 

QnOut

5.7% avg (n=30)
17% max
2.2% min

2.4% avg (n=86)
18.9% max
unmeasurable min

2.5%** avg
(n=59)

Qnout≤3%

5

73

 

Ratio of QnOut to Qntotal

56% avg (n=30)
80% max
20% min

36% avg (n=80)
80% max
0% min

50% (apprx) avg (n=59)
60% max
24% min

Source

See References, Data Sources

 (MHRA, 2003)

*Floor refers to a single wide or one section of a multi-section manufactured home.
**MHRA estimated Qnout. see QnOut compared to Qntotal,, p. 17




Figure 7. BAIHP Duct Data Averages
Top: Averaged CFM25Total and CFM25Out data show that mastic sealed systems were tighter than taped systems in both total leakage and leakage to the outside.
Bottom: Averaged Qntotal and Qnout data show that mastic sealed systems, on average, met both the total leakage and leakage to outside goals whereas the taped systems met neither.

Figure 8. All Qntotal data points for taped systems. Note that average (black line) is well above target (red line). 19 tape sealed systems met the 6% Qntotal goal.

Figure 9. All QnOut data points for Taped systems. Note that 5 taped systems met the 3% Qnout goal.



Mastic Sealed Duct Systems

Of the 190 floors tested, 132 had mastic sealed duct systems. Researchers conducted 124 CFM25total tests and 86 CFM25Out tests.

Total duct leakage only was measured in 44 mastic sealed systems. Of those, 17 did not meet the Qntotal 6% goal (Table 7). Problems centered on dimensional coordination of duct components and misaligned pre-cut register holes in sub-floor assemblies, incomplete mastic application, imprecise cutting, and incomplete joints (eg tabs not bent).

Table 7 Mastic Sealed Systems Exceeding Target Leakage Rates

ID#

Floors

Qntotal

Problems Identified

27

2

10.1%

Holes in main trunk oversized for floor boots, left unsealed.

28

2

7.5%

Leakage at registers, furnace plenum, and joints. Many make-shift tools, take-off material unknown

51

1

8.0%

Leakage at registers, furnace plenum, and joints.

25

2

8.3%

No mastic on furnace plenum

13

1

 

No mastic on furnace plenum

45

1

6.7%

Mastic applied incorrectly

26

2

7.3%

No mastic on furnace plenum

29

2

6.8%

Make-shift tools; poorly fitted holes

60, 14

2

6.4%

Register installed under interior wall (inaccessible for sealing). Mastic applied incorrectly

47

1

6.5%

Tab-over boots not making contact with trunk line. Gaps in mastic application

50

1

6.1%

Leakage found at registers, furnace plenum, and duct joints.
Mastic applied inconsistently
Poor boot connections

Both total and outside leakage tests were conducted on 80 mastic sealed systems, of which 58 floors met both the Qntotal<=6% and QnOut<=3% goals. The remaining 22 floors were divided into three groups (Table 8):

  • Floors that met the QnOut but not Qntotal (n=14). Qntotal range: 6.1% to 9.7%
  • Floors that met the Qntotal but not QnOut goal (n=1) QnOut=4.1%
  • Floors that met neither goal (n=7).

Six of the 7 floors that met neither goal were tested during two initial factory visits. One of the factories did not pursue BAIHP recommendations and the other is working toward achieving the Qntotal 6%.

Table 8 Mastic Sealed Systems Exceeding Target Leakage Rates

ID#

Floors

Qntotal

QnOut

Floors that met the QnOut but not Qntotal (n=14).

24

2

9.0% (Fail)

1.6% (Pass)

43

3

6.5% (F)

2.5% (P)

87

2

9.7% (F)

1.0% (P)

91

3

6.6% (F)

2.6% (P)

97

2

6.5% (F)

1.5% (P)

98

2

6.1% (F)

1.2% (P)

Floors that met the Qntotal but not QnOut goal (n=1)

67B

1

6.0%  (P)

4.1% (F)

Floors that met neither goal (n=7).

100

2

8.9% (F)

3.4% (F)

39

2

9.7% (F)

3.4% (F)

54A

1

9.1% (F)

3.3% (F)

99

2

6.3%  (F)

3.1% (F)

Only leakage to the outside was measured in 7 mastic sealed systems. One floor had leakage too low to measure. All six remaining floors failed to meet the Qnout goal (Table 9.)

Table 9 Mastic Sealed Systems Exceeding Target Leakage Rates

ID#

Floors

Qnout

Problems Identified

124
125

1
1

18.9%
13.3%

No mastic on return or supply plenum. Holes cut with large knife described by researchers as a "machete" Misalignment of components throughout

127
128
129
130

1
1
1
1

11.5%
9.8%
9.3%
7.2%

Tested in field shortly after set-up.
All same manufacturer who is still in pursuit of Qnout <=3% goal.

QnOut compared to Qntotal

The MHRA study estimates QnOut(Table 6) using a measured Qntotal multiplied by the ratio of QnOut to Qntotal for a completed house from the same factory.

For example, if a completed house for Factory A was found to have Qntotal=7% and QnOut=3.5%, then the QnOut estimation factor for incomplete houses at Factory A would be 0.5 (7%/3.5%). The value of QnOut to Qntotal ratios found by MHRA ranged from 24%-60% (MHRA, 2003).

Field measurements in new site built homes (Cummings, et al, 2002.) and many of MHRA's field measurements in new manufactured homes show QnOut is often approximately half of Qntotal, and in the absence of field data, MHRA used 50% as the multiplier to estimate QnOut from the measured Qntotal (MHRA, 2003.) As mentioned earlier, the goal of Qntotal<= 6% originates from applying the 50% rule of thumb multiplier to obtain a  QnOut<=3% goal, which is the BAIHP recommended duct leakage level corresponding to the most stringent duct leakage level in the Manufactured Home Energy Star program.

BAIHP data includes 26 taped systems that researchers tested for both total and outside leakage. The average ratio of outside to total leakage was 56%, roughly agreeing with the rule of thumb. However, in the 80 mastic sealed systems, the average ratio of outside leakage to total leakage was somewhat lower than expected at 36%. There were 13 mastic sealed systems that met the Qnout 3% goal without meeting the Qntotal 6% goal.

This lower than expected ratio is perhaps due to the improved sealing at joints between duct components but not between the house envelope (e.g. subfloor or ceiling) and the air distribution system (e.g. supply boots and return plenums). Leakage where the supply boot joins to the house is part of the total leakage, but tends to be associated with leakage to the interior of the house.

Though the average ratio of outside to total leakage in the mastic sealed systems was slightly lower than expected (36%), the range spanned 0% (leakage to outside too small to register) to 80%. The data strongly supports that achieving a Qntotal of 6% signifies that the QnOut will be less than 3%. One exception was documented (QnOut=4.1%), proving that using Qntotal as a surrogate test for the QnOut goal is not a guarantee.

Quality Control: Tangible Success

An objective quality control strategy is essential to achieving tight duct construction. If air were visible to the naked eye, a visual inspection would reveal leakage sites in any given duct system. In the absence of visible air, managers and line workers will need to learn a way to evaluate their duct construction quantitatively using pressure testing equipment common to building science.

Initially, a standardized duct test on the factory floor provides an objective evaluation of current practice, repairs, and process improvements. Ultimately, pressure testing all duct systems replaces subjective evaluation with a tangible, objective measure of success: total duct leakage, CFM25total or a ratio of duct leakage to conditioned area, Qntotal. These surrogate measurements are shown by this data and other field studies (Cummings, et al, 2002. MHRA, 2002) to substantially correlate with duct leakage to the outside of completed houses, the factory's ultimate quality goal.

The support of BAIHP as objective, third party experts is often cited by manufacturers as a major benefit. Some manufacturers have already adopted the test procedure into their production process to conduct their own in-house verification of duct system tightness. This leads to a higher quality product as well as accountability of both the factory and field work force.

Continue to Economics of Duct Tightening in Manufactured Housing >>





BAIHP Home | Overview | Case Studies | Current Data
Partners
| Presentations | Publications | Researchers | Contact Us


Copyright © 2002 Florida Solar Energy Center. All Rights Reserved.
Please address questions and comments regarding this web page to BAIHP Master